Name and Address
|
Units
|
Capacity
|
Date of commissioning
|
|
Deenbandhu Chhotu Ram
Thermal Power Plant , Yamunanagar
Phone: 01732-298500
Fax: 01732-298501
|
Unit-I
|
300 MW
|
14.04.2008
|
|
Unit-II
|
300 MW
|
24.06.2008
|
The Government of Haryana approved the proposal of implementation of 2x300 MW Deenbandhu Chhotu Ram Thermal Power Plant Project Yamunanagar through International Competitive Bidding on EPC (turnkey) basis. Accordingly, a Letter of Intent (LoI) was issued on 30.09.04 to M/s Reliance Energy Ltd. (REL), Noida with the approval of Special High Powered Purchase Committee (SHPPC). Around 1107 acres of land was available for this project.
|
Salient Features of the DCRTPP Yamunanagar
|
Brief Information of the Project
|
Installed Capacity
|
2 X 300 MW
|
|
Available Land
|
1107 acres
|
|
Location
|
Yamunanagar
|
|
EPC Contractor
|
M/s Reliance Energy Ltd, Noida
|
|
EPC Cost
|
Rs 2097 crore ( Total estimated cost Rs.2400 crore)
|
|
Administrative approval
|
22.07.2002
|
|
Project Consultancy
|
M/s Desein was appointed Project Consultant and CEA were engaged as Review Consultants
|
|
Coal Sources
|
Central Coal Fields
|
|
Equity contribution
|
State Govt. is contributing 20% equity for the project vide letter dated 10.10.2002. Balance 80% has been arranged through PFC.
|
|
Issue of LOI
|
Issued to M/s REL vide letter dated 30.09.2004
|
|
Revised Zero date of Project
|
20.08.2005
|
|
Synchronization
|
300 MW Unit – 1 : 13.11.2007
300 MW Unit – 2 : 29.03.2008
|
|
Trial Operation Completed
|
300 MW Unit – 1 : 14.04.2008
300 MW Unit – 2 : 24.06.2008
|